August 2010 Photo's of RailRoad Progress

 

August 7, roadbed work on the mainline extention begins. First photo shows start in Macon and the last where the reverse loop starts.

 

August 21, on a day interupted by rain, the passing siding in Macon is started.

 

August 28, today began trenching and installing water and signal conduits along mainline extention.
Another crew flagged the path of the new track and plotted location diamond at the interchange with Sanford.

 

 

 