March 7th work began on adding a siding in the Sanford yard area. These photos show the roadbed prep in process.
Meanwhile, a switch is built and then put in place and track panels positioned.
At the passenger station, brick pavers are placed to complete the platform.

 

March 21st, the new passenger siding in Sanford was ballasted.
These photos show the diamond in the cross-over in Sanford Yard being built in place (with a great deal of help from a friend of the railroad).

 

March 28th, another switch for the yard is completed. Photos below show electrical work progressing at the Dade City Station.

 

 