July 3rd crews ballasted about 300 feet of track and leveled a portion at the north end of Sanford Yard.
Work also continued on the car barn extension.
These photos are from our 4th of July picnic and night run.

 

July 18, the last switch for the north end of Sanford Yard is completed and put in place.
This series of photos show the now completed car barn extension and the stub switches leading to it under construction.

 

July 25th, this series of photo's show the construction of stub switches, track and walkway in the car barn extention.
This photo shows the now completed and assembled ladder at the north end of Sanford Yard.

 

 