August 2009 Photo's of RailRoad Progress

 

August 1, crews ballasted the tracks to the car barn extension, then started on the main yard. Also track panels and a switch.

 

August 15, another switch for the yard nears completion.
Aid comes to the assembly crew.
Here, the switch is put in position and connected. This completes the first through track in yard.
Club engine gets some needed maintenance and put back in service.
Maintenance on steam engines takes lots of time.

 

August 29th, one crew cut up donated wood for ties another assembled another switch.
Here the last switch for the ladder at the south end of Sanford Yard is placed. Additional photos show completed ladder.

 

 

This page copyright ©2006-2009, Central Pasco & Gulf Railroad, Inc.All rights reserved.